Approval to Demolish Shah Alam Stadium Given Under Strange Circumstances
Publicly unpopular project taking more twists and turns
Murray Hunter
The Shah Alam City Council (MBSA) has finally issued a demolition notice (Kelulusan Merancang) for the Shah Alam Stadium, after a delay of several months. Most strangely, the demolition notice has been issued without any appointment of a project developer, project consultant or building contractor. The notice issued on Christmas day, leaves many questions that need answers.
Clandestine Constitutional Crisis
According to a senior state government officer the local government
order was given without any discussion within the State Assembly,
executive council, or even the state legal advisor. Further, the senior
state government officer said the Shah Alam City Mayor was under
pressure from the palace to issue the demolition order.
Local adjoining communities are against the project, as well as many state civil servants. The state bureaucracy has been very slow to progress this project, thus hindering the finalization of the project. Word around Shah Alam is even the chief minister Amirudin Shari is hesitant over the demolition. It was reported in Bulletin TV3 that the chief minister was not his personal wish.
“Ia berikutan, pembangunan itu bukan hasrat peribadi beliau sebaliknya ia hasrat Sultan Selangor, Sultan Sharafuddin Idris Shah; Raja Muda Selangor, Tengku Amir Shah dan penyokong bola sepak Selangor”.
(English translation: It follows that the development is not his personal wish but rather the wish of the Sultan of Selangor, Sultan Sharafuddin Idris Shah; Raja Muda Selangor, Tengku Amir Shah and Selangor football supporters.)
According to reports, TNB has not yet removed transformer installations from the site.
The whole stadium area has been designated a restricted area to prevent community protests.
The issuance of the demolition notice brings Section 55(2) of the Selangor Constitution into question. Section 55 clearly states that the Sultan must act on the advice of the executive council or a member who is acting under authority of the executive council, in exercising his function under the Constitution.
Thus, the issuance of the demolition order may in fact be unconstitutional. The state legal advisor must give an opinion on this matter.
Shah Alam Stadium Developer not yet selected
MRCB was previously announced as the strategic partner of the Shah Alam Stadium project. The company has already invested in some of the preliminary aspects of the project – planning and design. However, MRCB has only received a letter of intent from the Selangor State Government.
There is talk of another company, Blueprint Projects Sdn Bhd taking up some form of role in the project. The Companies Commission of Malaysia (SSM) registration shows that Blueprint Projects nature of business includes engineering contracting, building and investment property construction and consultancy. However, the company only has a paid-up capital of RM 1.0 million. This company is 70% owned by Tengku Amir Shah Ibni Sultan Idris Shah, the Raja Muda of Selangor.
Currently in Shah Alam there is great speculation as to why MRCB has not yet been officially appointed as the project contractor, and what (if any) will be the role of Blueprint Projects Sdn Bhd?
Why would the stadium be demolished if there is no contractor appointed?
This is a real mystery. Why would the Shah Alam City Council issue a demolition certificate for the Shah Alam Stadium without there being any appointed contractors? Rumour has it that there is not any complete agreement about which prime pieces of land the Selangor State Government should hand over to the contractor for the RM3.28 billion project.
Most importantly, why is there no public tender process for such a massive project in Selangor? This appears an exorbitant price to pay for such a project.
Should there by a massive Shah Alam Stadium site in the first place?
The original estimate to refurbish the Shah Alam Stadium was estimated by the Jabatan Kerja Raya (JKR), or Public Works Department, to cost around RM 154 million. The tender papers sent out for the project specially specified a refurbishment. The cost of repairing the roof alone is only RM 10 million according to one of the original companies tendering for the refurbishment project.
Then it was announced in the media,
with total surprise to the tenderers, that there would be a complete
redevelopment of the Shah Alam Stadium Complex, adding in a shopping and
commercial complex costing around RM 787 million.
Project papers approved by the State Executive Council actually approved the Shah Alam Stadium redevelopment at RM 3.28 billion. This is a staggering difference from an RM154 million refurbishment, and RM 787 million redevelopment.
So the repair costs to the roof of the stadium blow out from RM 10 million to RM 3,28 billion. The Selangor citizens are being taken on a massive ride. The capacity of the new stadium will only be a little over have of the existing stadium. Certainly not large enough to play a backup role to Stadium Bukit Jalil. If an event cannot be held at Bukit Jalil, Shah Alam Stadium is the alternative.
The Shah Alam Stadium has a sister stadium
The estimated life expectancy of the Shah Alam stadium is between 100-130 years. The Shah Alam Stadium was modeled on the Stadion Poljud in Croatia. This stadium was built in 1979 and refurbished before the 2010 IAAF Continental Cup Athletics, where the capacity was increased from 55,000 to 62,000.
Stadion Poljud in Croatia
The Shah Alam Stadium was built in 1990 and still has a potential long-life expectancy ahead of it. Why is the Selangor government even contemplating the demolition of the Shah Alam Stadium.
The question is why is the true cost of this project subject to the Official Secrets Act (OSA)?
It’s not too late to delay the project and undertake a transparent study, when RM 3.28 billion of state (public land) is at stake.